Road/Infrastructure Construction
Should any road construction be scheduled, information regarding delays or re-routing will be provided on our Village News page. To find out information on specific projects please check the links at the bottom of this page periodically. Should you have any questions regarding road construction, please call our Community Department at 815-462-6490 during normal working hours.


I-80/Rt 30 Interchange Improvement Project

Construction work on the IDOT project to improve I-80 and RT 30 intersection and adjacent roadways has ceased for winter season. The work will continue in the spring, when weather permits.

Annual Motor Fuel Tax (MFT) Road Project

Completed for 2019, 2020 MFT will be announced in the Spring

Rt. 30 Water Main Replacement Project. - July 1, 2020

Vine Street south of RT 30 will be closed beginning Monday, July 6, 2020, and will be open no later than Friday, July 17, 2020. The detour will include Cedar Road, Haven Avenue and Nelson Road. Local traffic will be able to access the businesses and properties located on Vine Street via Haven Avenue.

The contractor has begun installation a new water main between Nelson Road and Church Street. The southern eastbound lane of RT 30 may be closed for installation of the new water main. 

The contractor is completing connections to the new water main between Nelson Road and Veterans Parkway. Additionally, they are installing the new water main along the south side of the street between Veterans Parkway and Vine Street. Installation of the water main will continue to the east. As the contractor installs the water main in this area, property owners will have restricted access to their driveways during the time the contractor is installing the new water main. This work will be completed as soon as possible and stone placed in the trench to provide access. All driveways will have access by the end of the day.

Please contact Will Nash in the Engineering Department at 815-462-6490 or  wnash@newlenox.net with any questions or concerns you may have.

Construction of the Rt. 30 water main replacement and upgrade extending from Church Street to Nelson Road were financed by the Drinking Water State Revolving Fund (SRF). The SRF program is administered by the Illinois Environmental Protection Agency and receives a portion of its money to fund these types of projects from the U.S. Environmental Protection Agency. This project includes replacing main valves, hydrants, and service valves. Also included is the replacement and upsizing of the existing 40+ year old 8 inch water main to 12 inch. Once complete, it will improve water quality for area residents and businesses in New Lenox by increasing the flow capacity and reducing the number of supply issues due to water main breaks. SRF programs operate in each state to provide communities the resources necessary to build, maintain, and improve the infrastructure that protects one of our most valuable resources: water.

Metra Train Station Construction - April 30, 2020 Update

Daily Parking Fee is suspended until further notice.

The contractor is working on construction within the new building area. Parking is this construction area is prohibited.

Access to the east end of the train platform is restricted, pedestrians will need to access the platform near the temporary METRA ticket office. This area will be under construction until approximately November of 2020. Pedestrians will be able to walk along the south side of the construction area via a pedestrian walkway protected from traffic by a barrier wall. Additionally, the parking pay stations have been moved to an area near temporary METRA ticket trailer.

The east parking lot is open for use, and pedestrians can access the train platform via a pedestrian walkway along the south and west sides of the constriction area.

The east parking lot can be only be accessed from Prairie Road. The west parking lot can only be accessed from Cedar Road. The middle lot is closed for construction and there is no access between lots.

Construction updates will be provided on the Village of New Lenox Website at www.newlenox.net along the left hand side under Road/Infrastructure Construction.


       
       
       

       